The reporter learned from the Port and Shipping Development Center of Guangxi Zhuang Autonomous
Region that up to now, the Guigang-Wuzhou 3000-ton waterway project has completed an investment
of 54.254 million yuan in the first quarter, which has completed more than 60% of the quarterly target
tasks.
"We will not take a holiday if the 3rd standard is not completed." Yang Yuanyun, deputy manager of
the No3 standard project of the first phase of the project, expressed his determination to stick to
his position during the Spring Festival, "We are serious about channel improvement." Currently,
the No3 standard only has Yanshe beach. The remaining 7 beach points have successfully passed
the joint inspection and acceptance. During the Spring Festival holiday, the tender section was
under normal construction, and 5 reef bombers and 3 dredgers(including silt curtains) were
arranged to focus on the salt snake beach. Up to now, the Yanshe beach has accumulated
56775 cubic meters of dredging, 57274.1 cubic meters of reef bombing, and 55659.7 cubic
meters of slag removal, with an output value of more than 26 million yuan.
According to reports, during the Spring Festival, the main construction of the Guiwu
Channel was started. Each bidding section focused on the target and tasks of the first
quarter. According to the Spring Festival construction plan formulated at the beginning
of the year, the equipment and personnel were organized to work overtime. At present,
the projects of the first phase of the project have successively entered the stage of
sweeping acceptance; the second phase of the project is difficult to construct and
the task is heavy,it will require large-scale tackling and lay a good foundation for
the follow-up of the project.