Since the construction of the Yangjiang Port’s approach channel renovation project
started in June this year, it has now entered the full construction stage. The
channel has been expanded on the basis of the original 50,000-tonne channel
to the 100,000-tonne navigation standard. After the completion of the project,
the level of the port will be further improved, the navigation capacity will be
effectively solved, and the sea passage in our city will be smoother. The
reconstruction and expansion project mainly includes channel dredging,
mud storage pit and mud channel excavation, navigation mark engineering,
and obstruction removal. It was dispatched dredger, and then used silt curtains
for controlling the silt, and then cleaned the silt .The depth of the channel was
dug from the original minus 12 meters to minus 15 meters, and the width of
the channel bottom was widened from the original 150 meters to 230 meters.