The total length of the waterway from the Lishui Shimen to Lixian Waterway Construction Project
is totally 51 kilometers long. The starting point is Shimen Zhaoheng Industrial Park and the end point
is Jinji Beach, which is connected with the completed 1,000-ton waterway project of Maocao Street
in Li County.
The project construction mainly includes the expansion of ship locks and channel dredging. Among them,
the two ship locks of Qingshan and Yanzhou are rebuilt and expanded according to the 1,000-ton standard,
and the Qingshan sluice, Yanzhou power station and sluice are simultaneously rebuilt. The 51km waterway
project from Shimen to Lixian was renovated according to the level 3 standard, including waterway renovation
by dispatching dredging ships with dredgers and silt curtains and reconstruction of obstructed bridges. The
estimated investment of the project is 3.598 billion yuan, and the provincial water transportation construction
investment group Co., Ltd. is responsible for the construction. According to the preliminary work advancement
requirements of the key water transportation construction project of the Provincial Department of
Transportation, the project is scheduled to be completed by the end of July this year, the preliminary design
approval will be completed in early August and the construction supervision bid will be started, and construction
will begin in November.