The Zhapo Modern Fishing Port project has been fully resumed. On the morning of the 19th, the
reporter learned that the dredging project for the harbor and waterway in the fourth tender
section of the project is currently entering the tailing stage of the project, and the fourth tender
section is expected to be completed in two months.
According to the person in charge of this Project said, the total investment in the dredging
project of the fourth bid section of the Zhapo Fishing Port is over 23 million yuan, with a total
dredging area of 1.621 million square meters. After the project is completed, the water depth
of the entire port area can reach five to six meters. The new high-piled wharf section has large
stones underwater in the open channel, and the volume is large, which poses a great safety
hazard to passing ships. If the stones are not removed in time, it will affect the docking of the
fishing boats at the new high-piled wharf. After research and judgment by experts, relevant
departments of the Hailing Test Area adjusted the construction plan to eliminate hidden safety
hazards.It will use silt curtains and excavators.
Huang Quanbei, the person in charge of the project said the project has been completed more
than 90% now, mainly for dredging the harbor basin. Now there are more than 10,000 cubic
stones in the outer channel. , it can be completed in two months if everything goes well.