Chassis Town used three hook machines, a dump truck and a crusher to operate for 11 consecutive days,
the Lancan Village section of Sugaiyinggou, the emergency channel in the southwest of Shibingdi Village,
and the channel in the south section of the Sikoong bridge of Youhao Village, the drainage ditch of the
Wanyacun section Wanshengqu and the Heqi Section have been dredged and reinforced. Up to now,
a total of 4.7 kilometers of rivers have been cleared. At the same time, they organized staffs to salvage
and clean up floating objects in the river and white garbage on the shore.It was used silt curtains and
dredgers.
Through this dredging and consolidation work, the channel diameter was effectively widened, the river
dam was strengthened, the phenomenon of river channel ditch blockage was improved, the river flood
protection, drainage, irrigation, water supply and other functions were guaranteed, and the property
security of.people were protected.