86-13819027011

Tema LNG terminal project port and waterway dredging construction started

On February 14, Ghana Tema LNG terminal project port and waterway 

dredging construction started smoothly.


The total amount of dredging works for the Ghana Tema LNG Terminal 

project is 560,000 square meters. Under the careful organization of the 

project department, the dredging vessel “Hangyu 4102” was dispatched

on schedule, and the construction permit and other materials were 

completed before it entered the site. At the same time, the project 

department communicated with the Ghana Port Authority in advance 

of the ship construction liaison mechanism, and boarded the ship with 

the owner and the staff on the day of the ship's arrival to check and 

accepted the ship to ensure the smooth start of the dredging after 

the ship entered the site. It will also used silt curtains for controlling 

silt and garbage.


At present, the mileage of the slopes of the LNG terminal project 

has reached 264 meters, and 610 blocks of prefabricated blocks 

have been prefabricated. The caisson is prefabricated to complete

the pouring of three bases, and other sub-processes are being 

carried out in an orderly manner.

 

Get Started Now with Contact



Whats App Us