Fuzhou Mawei Kuiqi Area water dredging project (First Phase) will finish
in the end of this month. The construction of the second phase will be
started next month, and the construction of the interception and
landscape greening project will begin. It is expected that the effect
of the clean environment of Shuiqing River will be realized after the
Spring Festival next year.
It is understood that the water system comprehensive treatment project
(Phase I) project in the Kuqi area of Mawei District contains dredging,
sewage interception, landscape greening and new road construction,
with a total investment of 12,296,500 yuan. They will deployed
silt curtains and use dredger. The project is constructed in two sections.
One section is to enter the construction in August this year. The main
content of the treatment is the river dredging project, including the
Kuifeng River main canal and the Kuipuming channel (south of the
104 National Road). The dredging is 3,630 meters long, and the rivers
of Kuiqixi, Gushanxi, Niukengxi and other rivers (north of the 104
National Road) are dredged, and the dredging length is 1,076 meters.