Recently, the project acceptance team consisting of the town
engineering office, the audit office and the water farm station
has carried out project acceptance about Xincheng Village
2018 rural river dredging project. The working group inspected
the onsite dredging project, and agreed that the project was in
standard management, the quality of the project was excellent,
and the completion acceptance was successfully passed. In 2018,
Xincheng Village has totally dredged 13 rivers with a length of
5.29 kilometers. It was deployed silt curtains and using dredging
machines. Through dredging, the drainage capacity of river channels
and ditches has been improved, and the rural ecological environment
has been improved.