On August 30th, a project ship on the e Xinting section of Puyangjiang River
waterway was intensively carrired out dredging operations. It was deployed
silt curtains for dredging.The maintenance will completely eliminate the last
bottleneck of the implementation of the Haihe River transport in Zhuji, and
effectively promote the process of container waterway transportation in the
jurisdiction and realize the passing of the rivers and seas in the jurisdiction.
It is understood that this dredging and maintenance waterway was the
fourth-grade navigation of the 13.8-kilometer section of the Puyangjiang
Xintingbu to Yaogongbu Bridge, which was deposited at the end of 2010.
It was also the trial waterway, which is the only way for the first container
terminal to sea and rivers at the end of September. The project need
dredge about 70,000 cubic meters earthwork, and the estimated budget
is 4.3 million yuan. The construction period is scheduled to be completed
on January 9 next year.