The Linquan Section waterway regulation project in the Fenquan River of Fuyang is expected to be com

The reporter was recently learned from the Linquan Water Affairs Bureau that Linquan section

waterway regulation project has now entered the implementation phase and it is expected that

the project will be completed before the end of June 2018.

Fenquan River is the only navigable river in Linquan County. Currently, it is a Class VI waterway

that can only be seasonally navigated, and it is difficult to meet the needs of economic and social 

development in the hinterland. The Anhui section waterway regulation project will be constructed 

according to the restrictive Class IV waterway standards. It will dredge from Qiwan to Shaying 

River; the total mileage of the project is 74.6 kilometers, of which the Linquan section is about 45 

kilometers. The main construction contents were included dredging projects by using silt curtains

and dredger, bank protection projects, buoy engineering, bridge anti-collision projects and 

supporting projects. At present, the relevant departments of Linquan County are making joint 

efforts to promote the construction of the project. It is expected that by the end of October, 

temporary land selection and compensation will be completed for the project's temporary

dumping of mud, spoil areas, etc.

The relevant person from Linquan County introduced, after completion of the Anhui section

waterway regulation project in the Fenquan River, the navigation waterway class will be 

upgraded in two levels. The navigable vessels will be upgraded from the current 300 to 

1,000 tons,and the ship passage rate and turnover volume of the fairway will also be increased. 

It will play an active role in improving the Fuyang water network, water transport capacity, 

and assisting local economic and social development.

 